A shored basement excavation on a tight Del Mar lot, taken from bare dirt through footings and foundation slab to fully reinforced and grouted CMU basement walls.
A downhill lot with neighbors on both sides and no room to work — the kind of site where the shoring, the drainage, and the sequencing matter as much as the concrete. 4x8 handled the foundation excavation interface, waterproofing and drainage at the shoring face, the footings and foundation slab, and the reinforced CMU basement walls that came up out of it.
Foundation work staged inside a shored cut against the neighboring properties, with the pad graded and compacted to spec.
Perimeter drain and waterproofing detailed at the base of the shoring wall before any structure went in.
Continuous and spread footings tied into a full reinforcing mat and vapor barrier, inspected before the pour.
Block basement walls laid, reinforced, and grouted solid — pump-placed on a site with no truck access.
Send the plans — shoring interface, drainage, slab, and block, priced as one scope.
Send Us Your Plans